Sunday, March 29, 2009

March 24, 2009

We started building our frame today. Since we were supposed to finish the base yesterday, we were a little behind. So we made sure we didn't waste any time. We also got the vertical support and the base done today. We also got our platform in for the projectile.

March 23, 2009

We started scavanging for wood. Since we are short on new supplies, we had to reuse the parts we used for our car a couple of months ago. But we are still entitled to some of the newer pieces of wood. A lot of people were using the electric saws and drills so we didn't get to cut our pieces of wood but we did get to mark how much of the wood we needed.

March 20, 2009

We really didn't do much. We just did the bill of materials or Jessica did. After that, we had to wait for Mr. Tator to approve it.. For the bill of materials, we had to list what materials we needed. We had to list what it looks like, what the part is for and how much we needed the material.

Friday, March 20, 2009

March 19, 2009

I was finising some final touch ups on my trebuchet. For example, putting as much details as possible so that Jessica, our construction manager, can do the bill of materials no problem. I was trying to get an accurate srews and bolts put on my sketch up. Another thing I was thinking about was how long the string would be and how heavy the weight is going to be. We haven't decided yet so that part is still unknown.

Wednesday, March 18, 2009

March 18, 2009

Today, Mr. Tator checked on every groups' progress. He was checking the sketch up design for every group and the crest design. My sketch was doable except with a a few additions. For example, I need to add support sytems on the middle wood so it wouldn't wobble. I added another piece of wood for both biddle wood pieces.

March 17, 2009

We didn't do ant work on our trebuchet project.

March 13, 2009

We didn't do anything on the trebuchet.